Three kiln live rings from Marghera to Mumbai required a special port exit operation before onward project-site delivery.

July 2022
Cargo3 kiln live rings
Largest unit7.52 x 7.52 x 1.2 m
Maximum unit weight90 MT
Special operationOver-the-wall port exit

01 / Project overview

A coordinated approach.

The July 2022 cargo was too wide to pass through the Mumbai Port exit gate. The project team obtained special permission from the port authority to move it over the wall.

The project record documents successful execution. The scope also covered ocean chartering, destination clearance, handling and transportation to the project site.

The route

Key locations in the project scope

  1. Ocean charter
    01 / Loading port, ItalyMarghera
  2. Site transport
    02 / Special port exitMumbai
  3. 03 / Final deliveryProject site

02 / Our execution

From readiness
to delivery.

Ocean chartering, port clearance, handling and site transport.

Project scope

Ocean chartering

  1. Ocean chartering

    Move three kiln live rings from Marghera Port, Italy, to Mumbai.

Movement

Special port operation

  1. Special port operation

    Obtain permission and execute the over-the-wall movement for cargo unable to use the standard exit gate.

Delivery

Project-site movement

  1. Project-site movement

    Coordinate destination clearance and handling, followed by transportation from the port to the project site.

04 / Project highlights

A special operation for oversized cargo.

3

Kiln live rings

90 MT

Maximum unit weight

7.52 m

Maximum unit width