Cell line logistics through dedicated trans-shipment.

GOPIN Semicon Pvt. Ltd.

A two-lot programme for solar cell manufacturing equipment, with Lot 1 delivered to Hazira and a second, 2GW lot described in the source.

GOPIN Semicon Pvt. Ltd. project photograph 1
Lot 1138 containers / completed
Lot 1 destinationHazira
Lot 2366 containers / 2GW capacity
Lot 2 originsShanghai and Shenzhen

01 / Project overview

A coordinated approach.

Lot 1 moved through physical trans-shipment to Hazira, with offload, bonded-zone storage and reload supported by a continuous compliance record. Arrival at Hazira is recorded as 17 June 2026.

The project record describes Lot 2 as a 2GW programme: 133 containers from Shanghai and 233 from Shenzhen. It records customs completion in June 2026 and scheduled departures in July 2026.

The route

Key locations in the project scope

  1. Origin voyage
    01 / Shanghai / Shenzhen originsChina
  2. Onward voyage
    02 / Bonded-zone offload & reloadTrans-shipment port
  3. 03 / Indian destinationHazira

02 / Our execution

From readiness
to delivery.

Dedicated trans-shipment for ODC cell line equipment.

Lot 1

Origin & physical trans-shipment

  1. Origin preparation

    Secure all containers inside the origin port; vessel arrival was recorded on 22 May and departure on 24 May 2026.

  2. Bonded-zone handling

    Arrive at the trans-shipment port on 30 May, fully offload to a bonded zone, then reload and depart on 7 June 2026.

Lot 1 delivered

Hazira arrival & compliance

  1. Arrival at Hazira

    Record arrival on 17 June 2026, completing the 138-container movement.

  2. Unbroken audit trail

    Maintain regulatory compliance through offload, storage and reload, with zero damage, documentation queries or delays reported for Lot 1.

Lot 2 recorded plan

Two-origin programme

  1. Shipment A - Shanghai

    133 forty-foot containers: 87 flat racks and 46 high cubes. Customs completion was recorded on 29 June 2026.

  2. Shipment B - Shenzhen

    233 containers: 111 forty-foot flat racks, one twenty-foot flat rack and 121 high cubes. Customs completion was recorded on 30 June 2026.

03 / Project timelines

Milestones in focus.

Lot 1 - completed

138 containers: 86 forty-foot flat racks and 52 forty-foot high cubes.

  1. Before departureContainers gated inCompleted
  2. 22 May 2026Vessel arrival at originCompleted
  3. 24 May 2026Origin departureCompleted
  4. 30 May 2026Arrival at trans-shipment portCompleted
  5. During trans-shipmentPhysical offload to bonded zoneCompleted
  6. 7 June 2026Reload and departureCompleted
  7. 17 June 2026Hazira arrivalCompleted

Lot 2 / Shipment A - Shanghai

133 containers. Status reflects the supplied June-July 2026 record, not a current tracking update.

  1. 20 June 2026PickupRecorded complete
  2. 25 June 2026Stuffed and gated inRecorded complete
  3. 29 June 2026Customs completionRecorded complete
  4. 7 July 2026Vessel ETDScheduled in source

Lot 2 / Shipment B - Shenzhen

233 containers. Current completion status awaits an updated project record.

  1. 21 June 2026PickupRecorded complete
  2. 27 June 2026Stuffing completedRecorded complete
  3. 30 June 2026Customs completionRecorded complete
  4. 9 July 2026Vessel ETDScheduled in source

04 / Project highlights

Lot 1: 138 containers delivered with zero incidents.

138

Lot 1 containers

86

Lot 1 flat racks

52

Lot 1 high cubes

366

Lot 2 planned containers