Renewable Energy & Solar
Cell line logistics through dedicated trans-shipment.
GOPIN Semicon Pvt. Ltd.
A two-lot programme for solar cell manufacturing equipment, with Lot 1 delivered to Hazira and a second, 2GW lot described in the source.

01 / Project overview
A coordinated approach.
Lot 1 moved through physical trans-shipment to Hazira, with offload, bonded-zone storage and reload supported by a continuous compliance record. Arrival at Hazira is recorded as 17 June 2026.
The project record describes Lot 2 as a 2GW programme: 133 containers from Shanghai and 233 from Shenzhen. It records customs completion in June 2026 and scheduled departures in July 2026.
Key locations in the project scope
- Origin voyage01 / Shanghai / Shenzhen originsChina
- Onward voyage02 / Bonded-zone offload & reloadTrans-shipment port
- 03 / Indian destinationHazira
02 / Our execution
From readiness
to delivery.
Dedicated trans-shipment for ODC cell line equipment.
Origin & physical trans-shipment
Origin preparation
Secure all containers inside the origin port; vessel arrival was recorded on 22 May and departure on 24 May 2026.
Bonded-zone handling
Arrive at the trans-shipment port on 30 May, fully offload to a bonded zone, then reload and depart on 7 June 2026.
Hazira arrival & compliance
Arrival at Hazira
Record arrival on 17 June 2026, completing the 138-container movement.
Unbroken audit trail
Maintain regulatory compliance through offload, storage and reload, with zero damage, documentation queries or delays reported for Lot 1.
Two-origin programme
Shipment A - Shanghai
133 forty-foot containers: 87 flat racks and 46 high cubes. Customs completion was recorded on 29 June 2026.
Shipment B - Shenzhen
233 containers: 111 forty-foot flat racks, one twenty-foot flat rack and 121 high cubes. Customs completion was recorded on 30 June 2026.
03 / Project timelines
Milestones in focus.
Lot 1 - completed
138 containers: 86 forty-foot flat racks and 52 forty-foot high cubes.
- Before departureContainers gated inCompleted
- 22 May 2026Vessel arrival at originCompleted
- 24 May 2026Origin departureCompleted
- 30 May 2026Arrival at trans-shipment portCompleted
- During trans-shipmentPhysical offload to bonded zoneCompleted
- 7 June 2026Reload and departureCompleted
- 17 June 2026Hazira arrivalCompleted
Lot 2 / Shipment A - Shanghai
133 containers. Status reflects the supplied June-July 2026 record, not a current tracking update.
- 20 June 2026PickupRecorded complete
- 25 June 2026Stuffed and gated inRecorded complete
- 29 June 2026Customs completionRecorded complete
- 7 July 2026Vessel ETDScheduled in source
Lot 2 / Shipment B - Shenzhen
233 containers. Current completion status awaits an updated project record.
- 21 June 2026PickupRecorded complete
- 27 June 2026Stuffing completedRecorded complete
- 30 June 2026Customs completionRecorded complete
- 9 July 2026Vessel ETDScheduled in source
04 / Project highlights
Lot 1: 138 containers delivered with zero incidents.
Lot 1 flat racks
Lot 1 high cubes
Lot 2 planned containers